2010
|
Council decision to proceed with environmental and planning approvals. Commenced community engagement on site and technology options.
|
2011
|
Obtain environmental approvals.
Submitted Public Environmental Review of facility proposal to Environment Protection Authority.
|
2012
|
Public comment period on Public Environmental Review PER) document.
|
2013
|
Responded to public comments and regulatory queries on PER.
|
2014
|
Environmental approvals granted.
Consulted with member councils and decide whether to proceed with the tender process.
Decided to end the Expressions of Interest process.
|
2016
|
Council resolution to proceed with tender process.
Industry consultation process and further community engagement.
Commenced tender process.
|
2017
|
Concluded tender process, tender evaluation and selection of preferred tenderer.
Contract negotiation with preferred tenderer.
|
2021
|
Construction of the Resource Recovery Facility.
Operation of the Resource Recovery Facility.
|